Construction Progress Update 3-14-2018

Most work being done on the Phase 1 Buildings continue to be allocated towards Xcel and getting heat and electricity to those residences. When that is finalized, things like carpet, appliances, and plumbing fixtures will be able to start going in! Outside of Xcel, progress does still continue.

Stringers along the stairwells of Building A Residences were being installed today.

Light fixtures are going in Building B residences, today specifically they were being installed in 1228 E. Asbury (Residence 8).

Phase 2:

Building E – MEP work continues making steady mechanical and plumbing advancements throughout the five residences.

Building F – MEP is appearing to near completion on these residences as electrical boxes and fixtures are set. Insulation is stocked, drywall installation is not too far off in the future. (See picture)

Building G – Framing is now up all the way to the roof (see picture)

Stay tuned for more construction progress updates for Marion Place!


Construction Update - March 3rd

The homes on Marion and Asbury parallel with springtime themes, as the sight of the residences coming together makes you feel like whistling, even though your shoes are filled with slush and mud from the melted snow. Below are the updates.


Phase 1


Residences generally continue to be in an interim phase until gas is finalized, though the single family homes (buildings C&D) are progressing – both now have countertops installed in the kitchen and master bathrooms. Tiling in the master and guest bathrooms is sporadically being installed as well. (see attached pictures)

Phase 2


Building E now has rough electrical installed through residences 1258, 1268, and 1274 E. Asbury, and insulation was going in through all 5 residences today. (see attached pictures)
Building F also has insulation going in and drywall is stocked in each residence, ready to be hung. (see attached picture)

Construction Progress Update 11-28-2017

Progress continues at– a rapid pace with all buildings showing substantial developments each week. Below is a little summary of where each residence is at!

Building A) from South to North

Residences 1-3: The interior walls of these units are now textured through all 4 floors with the exception of the garage. Everything is ready for cabinets and tiles to start going in, which could begin very soon!

Residence 4 - The drywalls of this unit were being textured today!

Building B) From South to North on location:

Residence 1 - Drywall is hung and has undergone tape and mud and is ready to be textured.

Residence 2 - The drywall is being touched up with tape and mud today.

Residence 3 - Drywall is hung in this unit through all 4 floors now and is ready for tape and mud, which will occur when unit 2 is finished.

Residence 4 - Workers were hanging the drywall in this unit today.

Single Family Units

Building C & D – Both buildings are in similar points of progress with much of the rough plumbing and mechanical work being set and electrical going in.

Phase 2: Buildings E and F are starting to go vertical with framing up for the ground level.