Construction Update - July 10th

Preparation continues between the Phase 1 buildings for the paver work to commence.

All Phase 1 Buildings continue on punch items and finalizing of last minute modifications.

Phase 2:

Building G (Single Family – 2005 S. Downing) – Tape and Mud work was beginning today.

Building E (1288 E. Asbury – 1258 E. Asbury) – All five residences have completed tape and mud, they have been textured, and applied with white paint covering

Building F (2011 – 2021 S. Marion St) – All four residences have hardwood floors installed, cabinets installed in the kitchen and bathrooms, and general tiling work complete in the bathrooms. Light fixtures are also starting to be stocked. – residence 20, 2021 S. Marion, has installed light fixtures with the exception of the dining room chandelier.