Landscaping and Conduits

Building E (1288 – 1258 E. Asbury Ave): Work continues on the electrical and communication conduit lines between buildings E & F.

Building F (2011 – 2021 S. Marion St.) – Landscaping of the front exteriors along Marion St are scheduled to begin this week and capitalize on the nice weather.

Building G (SF 2005 S. Marion St.) – The kitchen chandelier and island pendants are installed as well as the kitchen backsplash.